Skip to main content

Bid #1881-2021 Summer Roofing Project Package #1

Scope of Work: 2021 Summer Roofing Projects at four elementary schools (El Monte, Meadow Homes, Walnut Acres, and Woodside). 

Work is expected to be substantially completed by August 3, 2021. 

Mandatory Meeting Date and Time:

January 26, 2021 at 9:30 a.m.

Mandatory Meeting Location:

1480 Gasoline Alley, Concord, CA

M&O Parking Lot

Opening Date and Time:

*********REVISED**********

February 12, 2021 at 9:30 am

Purchasing Contact:

Diana Engel-Holmes

engelholmesd@mdusd.org, Ext. 3750

Submittal Location:

Purchasing Warehouse Department

2326 Bisso Lane Concord, CA 94520

Project Manager: Charlie Beigarten , Ext. 3861
Engineer's Estimate: Not being supplied.
Class of License: B, C-39
District Policies and Procedures: See ALL MDUSD Bid Documents
Status:

Awarded/NOTICE OF COMPLETION: Board approved on 1/12/2022.

Disclaimer: Mt Diablo Unified School District advises that prospective bidders periodically check this website for modifications to bid documents. We are not responsible for a prospective bidder's misunderstanding of the bid solicitation or nonresponsive bid due to failure to check this website for updates or amendments to bid documents, and/or other information regarding the bid solicitations. Failure to periodically check this website will be at the bidder's sole risk.